Salman Tripod Renovation

This project consisted of PC package for renovation of existing piping manifolds and tripods of Salman field and it was signed between SAFF and PEDCO in Feb. 2006.  The project scope included 13 tripods and their relevant piping which included 11 oil lines and 10 gas lines. The total steel structure weight for this project was 252 tons.

 

Project Summary
 Location  Salman Oil Field
 Client  PEDCO
 Duration  11.5 months
 Start Date  Feb. 2006
 Scope

 PC Package for renovation of existing tripods and piping manifolds: 

  • Refurbishments of 13 numbers of the existing tripods structures
  • Removal of existing topsides piping of 13 tripods
  • Installation of new piping manifolds

 

  