Soroosh & Nowrooz Integrated Field Development

This project consisted of PC package for 3 jackets, 2 decks, 1 conductor tower and 1 bridge that was singed between SAFF and Hyundai for Shell in Feb. 2012. The project scope included 4000 tons of offshore steel structure.

 

 Project Summary
 Location  Soroush and Nowrooz Field
 Client  Hyundai for Shell
 Duration  12 months
 Start Date  Feb. 2002
 Scope

 Fabrication, Pre-commissioning, Load out and Sea  Fastening offer:

  •  SWP1 Jacket
  •  SWP2 Jacket
  •  NWP1 Jacket
  •  SWP1 Deck Including
  • NPP1 Drilling Deck
  • NPP1 Conductor Tower
  • SWP1 Bridge